Construction Law
(See Architect Engineer Law for discussion of 10 year statute of repose enacted by the Ohio General Assembly in 2005)
Recent Construction Law Developments
About requirements for contractors on federal projects to verify citizenship and
immigration status of workers, see Business Law Developments.
Incorporation of Arbitration Clause In
Acme Arsena Company, Inc., v. J. Holden Construction Co., Ltd.,
2008-Ohio-6501, the Cuyahoga County Court of Appeals held that the
incorporation by reference of the A201 general conditions in a contractor's subcontract
compelled the subcontractor to engage in arbitration for dispute resolution
in a dispute with the contractor for extra costs.
For a recent case on piercing the corporate veil for constructon defects, see Business Law discussion of
Winegar v. Creekside Crossing Home Sales.
Contract Procedures In Dugan &
Meyers Constr. Co., Inc. v. Ohio Dept. of Adm. Servs., 113 Ohio St.3d 226, 2007-Ohio-1687, the Ohio Supreme Court held
that a contractor's delay claims were barred by a "no damages for delay" clause in the contract. The court also said that the
contractor was not excused from complying with the change order procedure to get extensions of time. Ohio's Fairness in Contracting
Act, which voicds "no damages for delay" clauses, did not apply when this contract was signed.
Construction Managers In In
Wagner-Smith Co.v. Ruscilli Construction Co, 139 Ohio Misc.2d 101, 2006-Ohio-5463, a contractor in a multimillion dollar construction
project at the Ohio State University brought this action against the Ohio State University's construction manager for intentional interference w
ith the contract between the contractor and the Ohio State University. The Franklin County Court of Common Pleas held that the claim is barred
by the economic loss doctrine as set forth in Floor Craft Floor Covering Inc. v. Park Community Gen'l. Hosp. Assn. (1990) 54
Ohio St.3d 1, 560 N.E. 2d 206. Furthermore, the construction manager could not be liable for a tortious interference with contract claim
because of privilege: an agent cannot be liable for tortious interference unless that agents actions benefited itself solely in a personal capacity.
Differing Site Conditions In
Allied Environmental Servs., Inc. v. Miami Univ. (Ct. of Claims), 2006-Ohio-5668, an asbestos
removal contractor alleged differing site conditions from those set forth in the contract.
To prove that type of claim, the contractor must show: (1) that its contract contains an
affirmative indication regarding the subsurface or latent physical condition that forms
the basis of the claim; (2) that the contractor interpreted the contract as would a reasonably
prudent contractor; (3) that the contractor reasonably relied upon the contract indications r
egarding the subsurface or latent physical condition; (4) that the contractor encountered
conditions at the job site which differed materially from the contract indications regarding
the subsurface or latent physical condition; (5) that the actual conditions encountered by the
contractor were reasonably unforeseeable; and (6) that the contractor incurred increased costs
which are solely attributable to the materially different subsurface or latent physical condition.
In this case, the contractor failed to exercise due care in evaluating the work which it underbid.
Also, the contractor failed to give timely notice of the allegedly differing condition as required
by the contract.
In Trucco Constr. Co., Inc. v. Columbus, 2006-Ohio-6984,
the Franklin County Court of appeals held that the contract did not contain a representation of the site conditions,
to the excess groundwater claim of the contractor was properly decided against it on summary judgment. Another interesting portion of the case involved
Ohio municipal home rule powers. The court said that the Columbus City Charter authorized the adoption
of procedures that differed from those contained in RC 153.12 that requires a public owner to pay a "reasonable sum for
overhead" if the public entity fails to execute publicy with contracts within 60 days of the bid opening.
Mediation Confidentiality
In
O'Donnell Constr. Co. v. Stewart, 2006-Ohio-1838, an owner and a contractor settled a
dispute in mediation, by which the owner agreed to pay the contractor $100,000 in exchange
for the delivery of certain materials within 30 days. The owner refused to make payment
alleging that during the course of the mediation, the contractor had made fraudulent
statements inducing the settlement. At trial, the owner sought to compel the deposition
testimony of the mediator. The trial court issued a protective order to protect the
confidentiality of mediation communications. On appeal, the Court of Appeals affirmed
saying that the trial court did not abuse its discretion in applying the statutory
confidentiality for mediation communications.
Governmental Immunity
In
Hortman v. Miamisburg, 110 Ohio St.3d 194, 2006-Ohio-4251, the Ohio Supreme
Court said that when performing a governmental function, people have no right to rely on
what the government tells them or promises them, without a contract in writing. The
Hortmans alleged that they had suffered damage to trees during a road improvement
project by the City of Miamisburg, Ohio. Before the work started, the Miamisburg City
Engineer promised them that certain trees would not be touched or destroyed. When those
trees were destroyed, the Hortmans brought suit. Reversing the court of appeals, the
Ohio Supreme Court found that the City of Miamisburg was immune from liability for the
property damage, holding that the doctrines of equitable estoppel and promissory estoppel
are inapplicable against a political subdivision when the political subdivision is
engaged in a governmental function.
Remedy for Low Bidder
In
Cementech, Inc. v. Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, the Ohio
Supreme Court, reversing the court of appeals, refused to permit a disappointed low
bidder on a public project, who was not awarded the contract despite the low bid,
from recovering lost profits as damages. Ohio R.C. section 735.05 requires municipalities
to select the "lowest and best" bidder. In dictum, the court stated that a wrongly
rejected bidder is limited to injunctive relief.
Pay-If-Paid Clause Upheld According to Ohio's 10th District Court of Appeals in B.I.
Chipping Co. v. R.F. Scurlock Co., (12/20/05) 2005-Ohio-6748,
Ohio's Fairness in Contracting Act, RC 4113.65 does not invalidate a contract
provision in a subcontractor's contract that limits the subcontractor's delay damages recovery to whatever
recovery the contractor is able to secure from the owner. BI Chipping ("Chipping") was a subcontractor
to RF Spurlock ("Spurlock") on a highway job. When Chipping arrived on the job, the DOT
had failed to secure the relocation of telephone lines. Chipping requested $25,000
additional compensation. Spurlock took the claim to DOT who settled Chipping's portion
of the claim for $10,000. Dissatisfied with only $10,000, Chipping sued Spurlock. The
trial court dismissed on summary judgment and the 10th District Court
of Appeals affirmed, saying the parties had a right to and did enter into a contract that limited
Chipping from recovering anything from Spurlock that Spurlock could not recover from DOT.
To download and read the case, click on the case name.
|
|
Carroll,
Ucker & Hemmer LLC includes over 80 years of combined litigation
experience with over 30 years related to the defense of architect and engineer
malpractice claims as well as a variety of contract and other related business
matters.
Home
Business Law
Architect/Engineer Law
Construction Law
Arbitration/Mediation Law
Nonprofit & Charitable Solicitation Law
Personal Injury Law
Workers' Compensation Law
Misc. Cases
About Us
Links
Articles
Ohio's Trap: Make Enforceable Contracts with Public Entities. Are Your Local Government Contracts Valid? Are they enforceable?
Ohio law is very strict.
To Arbitrate or Not to Arbitrate?
When deciding whether to include an arbitration clause
in your contracts or to engage in arbitration voluntarily,
there are several factors to consider.
Ohio's Fairness in Contracting Act.
Some common "form contract" provisions are now against public policy.
What are your rights?
For the articles, click on the headlines.
|